Driving in Sheet Piles (Pier side reinforcement) on the end of pier and up-river side and completion of abutment concrete in parking lot.
| The pier from north of parking lot. You can see the length of the sheet piles that are being driven into the ground under the pier. | The pier from the end of the parking lot showing the sheet piles (Pier side reinforcement) being drive in to the area that has been so bad for the last few years. |
| Concrete pouring next to adbutment reinforcing storm drain pipe. Additional pouring on other side. | Not a lot to see, the re-enforcements are on the end and upriver side of pier. The pilings have been put in place for the wide walkway. Think they are getting ready to put in a room for Hank to live in? |